Once conditions allowed, our engineers returned to Minnesota to complete the offloading, unpacking, and installation of the machinery. Working in collaboration with an international partner, specialist lifting equipment was used to position the machines safely and accurately.

Installation works included:

  • Careful positioning and alignment of machines within the production line
  • Precision re-levelling to ensure machines were installed exactly to manufacturer specifications
  • Rewiring and re-oiling of equipment
  • Full commissioning of machinery and robotic systems

We remained on site beyond installation to provide post‑commissioning support, ensuring that the equipment was fully operational and production-ready before final handover.

Due to the extreme temperatures, local safety protocols meant engineers were transported directly between accommodation and site, underlining their commitment to seeing the project through despite challenging conditions.

Despite extreme weather, extended delays, and international logistical complexity, the project was successfully delivered with all machinery was safely relocated and reinstalled to original specifications.

This project clearly demonstrates our engineer’s flexibility, adaptability, and commitment to customer care. Rather than simply lifting and shipping machinery, the team took full ownership of the equipment from decommissioning through to final commissioning, remaining involved, returning overseas when required, and ensuring the machines were not only moved, but fully operational before leaving site.